This is the planned new garage for my bikes (see the arrow).
Planned to start summer 2004. (Started 2 years delayed)
|
 |
|
Building of MC garage started
W = 3,05/2,2 and L = 6,65 m.
(Only 2,2 m wide in the back)
Concrete filling August 24, 2006.
|
 |
|
Frost protection
Two layers, each 50 mm.
August 26, 2006.
|
 |
|
Wall
The blocks are in place and filled.
August 30, 2006.
|
 |
|
Wall finished
Surfaced September 2, 2006.
|
 |
|
Garage walls
Top level missing, September 17, 2006.
|
 |
|